WEEKLY CONSTRUCTION AND STREET WORK HIGHLIGHTS

Construction and Street Work Summary

Date: Week of June 11, 2018

WEEKLY CONSTRUCTION ARCHIVE

Construction and Street Work Summary

Date: Week of June 11, 2018

 

Dane Street Resurfacing

Tri-County Paving

Paving completed, will be restriped later this summer as part of City’s mainline striping

Questions should be directed to the City Engineer at 920-674-7700

 

State Street Water Main Replacement

Tri-County Paving

Water main and laterals completed.  Concrete curb and landscaping completed.  PW crews will be onsite pouring curb in select areas and backfilling behind curb.  Limited traffic access during construction.

Questions should be directed to the City Engineer at 920-674-7700

 

Park Street Water Main Replacement

Tri-County Paving

Water main and laterals completed.  Concrete curb and landscaping completed.  Concrete work has been completed.  PW crews will be onsite backfilling behind curb.  Limited traffic access during construction.

Questions should be directed to the City Engineer at 920-674-7700

 

Short, Copeland and First Street

Forest Construction

Water Department complete water services in select locations.  Fire hydrant will be installed on First Street.

Questions should be directed to Jefferson Utilities at 920-674-7711

 

E Linden Drive (between S Dewey and S Fischer Avenue) Manhole Repairs

Jefferson Public Works Department

Prior to resurfacing planned for later this summer, streets crews are completing manhole repairs.  Limited access to thru traffic while crews are on site. 

Questions should be directed to Public Works at 920-674-7737

 

N Copeland/W Short Street Concrete Curb Replacement

Jefferson Public Works Department

Prior to resurfacing planned for later this summer, streets crews are completing spot curb repair in advance of paving.  No parking is allowed while crews are working in the area.

Questions should be directed to Public Works at 920-674-7737

 

E Milwaukee Street

Jefferson Public Works Department

Prior to resurfacing planned for later this summer, streets crews are sawcutting and completing inlet repairs in advance of paving.  No parking is allowed while crews are working in the area.

Questions should be directed to Public Works at 920-674-7737

 

Old Firehouse Alley

Jefferson Utilities

Electric crew will be in Firehouse Alley and North Center Avenue.  Alley will be closed for various times but will be reopened each night.  Please use caution when driving through construction area.   

Questions should be directed to Jefferson Utilities at 920-674-7711

 

Brush Pickup

Jefferson Public Works Department

Brush pickup completed last week for the month of June.  Compost site is open during posted hours Wednesday, Friday, Saturday and Sunday for City residents to drop brush. 

Questions should be directed to Public Works at 920-674-7737